Builder and his son picked up the bunnies on Monday. Summer is now over, and the kids started school Thursday, 8/30. By Tuesday, insullation was completed and we passed that inspection. The Polish crew is cleaning up odd's and ends (leveling floors, minor trim & shingle work, French door banister, etc). I started paint prep for the exterior trim. Each of the kids, Josie and our friend Jenna helped, taking time to also clear rocks from the yard. Sheet rock has been delivered and installation is nearly completed on the second floor. Taping/plastering has started on the 2nd floor. Access to all of the exterior is rough, as I can't handle the scaffolding or 40' ladder by myself. Needed to get a yellow-jacket nest exterminated. The boys got into swinging a pick-axe to help level the back yard. Two big piles of dirt were moved from the front to the back,to allow level ground for the ladders.