All plumbing roughs delivered. Most plumbing rough completed (Jessica's very excited to see her tub installed). Electrical rough completed. Electrical fixtures are starting to arrive. HVAC install continued. Exterior trim and cedar shakes continue to get completed. Lines to septic worked on. All trenches, footings, gas tank and lines buried. Ground leveled, large rock removed from next to driveway and excavator now gone. Much work with building department re: clarrification on code for alarm system (each of four quotes interpreted laws differently). Downpayments for granite and cabinets made. Alarm service chosen (service will cost $250 annual, insurance discount will be $520 annual), will be installed 8/21. Researching soundproofing and multimedia, preparing trim bid (materials). Masons started, chimney done (big). Stoops next. Expecting mechanicals inspection next week. Installed blocking for towel bars, etc.