Wow, what a week! Monday started with the builder telling me the exterior doors were needed right away, and I needed to give all specs to the electrician and plumber. By the end of the week I had to remove trees and gut the living room ceiling. Cedar shakes and exterior window trim going on. LP gas tank buried. All old stoops removed. Electrician, plumber and HVAC started their work. Water in basement due to damage to Bilco door. While all mechanicals and carpenters were seeking my input, the architect was on vacation. Interior view (above) from mudroom entrance, through kitchen, to family room (old screen porch).