- Delivery of interior doors postponed another 4 weeks
- Delivery of kitchen island top postponed another 4-5 weeks
- Continued interior painting
- Continued installing interior trim
- Completed wiring all speakers and volume controls
- Mudroom tile sealed
- Boy's bathroom floor sealed
- Continued installing interior light fixtures
- Jessica's bathroom plumbing fixtures installed
- Kitchen plumbing completed
- Master bathroom tiled, completion pending additional tiles
- Staircase to 2nd floor removed and replaced
- Flooring moved out one week (11/19-23)
- Move-in date moved to 11/24.
pictures will be posted tomorrow (Monday).
- Delivery of kitchen island top postponed another 4-5 weeks
- Continued interior painting
- Continued installing interior trim
- Completed wiring all speakers and volume controls
- Mudroom tile sealed
- Boy's bathroom floor sealed
- Continued installing interior light fixtures
- Jessica's bathroom plumbing fixtures installed
- Kitchen plumbing completed
- Master bathroom tiled, completion pending additional tiles
- Staircase to 2nd floor removed and replaced
- Flooring moved out one week (11/19-23)
- Move-in date moved to 11/24.
pictures will be posted tomorrow (Monday).