Monday, October 29, 2007

Week Ending 11/3/07

- Jessica's Bathroom grouted & sealed
- Exterior painting
- Interior painting
- Trimwork
- Boy's bathroom floor grouted
- Mudroom tile layed
- Master shower mud base layed
- More fixtures installed
- The coming week is our last week to do any interior work before moving in
- Stairs to be replaced next Saturday
- Wood floors scheduled to be finished starting Monday, 11/12.
- Plan to move in Saturday, 11/17