This past week the floors were sanded, stained and polyurethaned. During this time we:- Confirmed trim design and materials
- Picked master bath stone and scheduled installation dates
- Scheduled delivery of master bath fixtures
- Re-picked kitchen island stone, scheduling installation
- Repaired basement exterior door (damaged in flood, and need for C. of O.)
- Exterior painting
- Interior trimwork
- Closet systems
- Sound system now functioning
- Cleaning, and lots of it
- Began moving in
As we celebrate all that we have to be thankful for, we prepare for the inspection for our Certificate of Occupancy on Monday, and the move from our New Canaan apartment to our new home before the end of November.