Friday, October 12, 2007

Week Ending 10/13/07





A rough week. In addition to general orchestration:
- Door order placed
- Trim package bid out
- Tiling Jessica's bathroom
- Picked tile for boy's bathroom
- Kitchen & Jessica's bathroom plumbing fixtures delivered
- Porto potty removed
- Heavy rains backed up where construction debris left, gutters overflowed. Result was 3" of water in the basement on Thursday night. Once trenches dug flow stopped entering house. Damage significant.
- Surveyer reported house over the alloted 20% allowance. Architect blaming builder. Builder blaming architect. Zoning not yet informed. Violation = 11 square feet.
- Kitchen cabinetry delivered and 1/2 installed.