- Continued painting exterior trim
- Gutters installed
- incorrect window trim replaced
- Exterior French door handles installed
- Front and mudroom doors stained
- Picked up tile for Jessica's bathroom and began dry layout.
- Reinforced mudroom floor from the joists underneath, to provide strength while keeping the tile on level with the 1st floor oak flooring.
- Met with cabinet maker for final kitchen details and plans for bathroom vanities.
- Created timesheet for October push (as we hope to be in before November), coordinating with all trades. Inspection for C/O should be possible by 10/29, if everyone is on time...